LATEST - CORE PREP TEST
What is the purpose of installing an auxiliary boom point sheave to the main boom tip?: Separate hoist lines
A designated Lift Director shall be assigned by the ?: Site Supervisor
Who is responsible for calculating net capacity?: Crane Operator
Who is responsible for ensuring all rigging is supervised by a Qualified Rigger?: Site Supervisor/ Lift Director Who is responsible for ensuring the crane owner is notified of any damage to the crane
or replacement/repair of wire rope?: Crane User
Who is responsible for restricting unauthorized access to the crane's work area?: Site Supervisor/Lift Director Who is responsible for ensuring crane operations are stopped if alerted to an unsafe
condition?: Lift Director
If the operator or A/D determine that ground conditions are not suitable for the equipment being operated, they should request the correct the issue: Controlling Entity Who is responsible for ensuring that personnel involved in crane operations understand their responsibilities, assigned duties and associated hazards?: - Lift Director When can the operator of a crane set the crane up with less than fully extended
outriggers?: When the load chart allows
The outrigger pad and cribbing should be strong enough to support?: The total weight of the crane and the load What must be known prior to setting up your crane?: Location of under- ground vaults What is the minimum distance the flange on the hoist drum should extend above the
last wrap of rope?: ½ inch
Eccentric main boom tip reeving will: Twisting of the boom 1 / 2
LATEST - CORE PREP TEST
What is the most common wire rope used on most cranes?: Right regular lay
Prior to leveling a crane what should be done with the outrigger jack?: Se- cure the float pad to jack cylinder What three functions will not work after two-blocking a crane that has a prevention
system?: Boom down, extend the boom and hoist
Boom angle on a telescoping boom is measured from above or below horizontal to the
?: Longitudinal axis of the boom base section
The line pull of the innermost layer on the hoist drum is than the outermost layer.: Greater
Side loading of a crane can be caused by?: Wind
If power fails to the crane what must the operator ensure is done?: The controls are put in the neutral position
On a multiple crane lift, do not exceed of the load chart.: 75%
If a crane operator knows the boom length and the boom angle he could use the range
diagram to estimate what ?: Load radius
Which of the following jib offsets will have the least amount of capacity?-
: 30 degrees
When is it okay to make modifications to the structure of the crane's upper works?: With written permission from the manufacturer
A sudden stop of the hoist on a crane will produce a what?: Dynamic load
When hoisting personnel from a crane, what must be on the crane?: -
Anti-two block device
What grade of alloy steel chain should be used for hoisting slings?: 80
Each time a line passes from the boom point to the load block it is considered a ?: Part