Oregon Commercial General Contractor Level 1 (CGC1) Practice Exam Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf
- Which of the following is the primary purpose of the Oregon
- Regulate union labor rates
- Provide construction loans
- License and regulate contractors in Oregon
- Approve architectural plans
Construction Contractors Board (CCB)?
Rationale: The CCB is responsible for licensing and regulating
contractors to ensure legal compliance and consumer protection.
- What is the minimum experience requirement to apply for a CGC1
license in Oregon? 1 / 4
- 1 year of residential construction
- 2 years of commercial construction
- 4 years of verifiable construction experience
- 10 years in any trade
Rationale: Oregon requires applicants to have at least four years of
verifiable construction experience, which may include apprenticeship, journeyman work, or supervisory roles.
- Which type of insurance is required for all Oregon commercial
- Life insurance
- Workers’ compensation insurance
- Vehicle insurance
- Health insurance
contractors?
Rationale: Contractors must maintain workers’ compensation
insurance to protect employees from on-the-job injuries.
- What is a primary responsibility of a commercial general contractor?
- Only perform electrical work
- Only manage finances
- Oversee all aspects of construction projects, including
- Only submit building permits
subcontractors
Rationale: A commercial general contractor manages the entire
construction project, coordinating trades, schedules, and compliance. 2 / 4
- Which of the following documents is required before starting
- Sales contract
- Building permit
- Mortgage statement
- Contractor insurance certificate
construction in Oregon?
Rationale: A building permit ensures that construction complies with
local codes and safety regulations.
- When a contractor hires subcontractors, which is the most important
- Verbal agreement
- Written subcontractor agreement
- Letter of intent
- Purchase order
document to have in place?
Rationale: A written agreement outlines scope, schedule, and
payment terms, reducing legal risk.
- What is the maximum fine for unlicensed contracting in Oregon?
A. $500
B. $1,000
- $5,000 per violation
- $10,000 per violation
Rationale: Oregon law imposes fines up to $5,000 for unlicensed
contracting to enforce licensing compliance. 3 / 4
- Which of the following best describes the role of a bid bond?
- Guarantees project completion
- Guarantees subcontractor payment
- Ensures the contractor will enter the contract if awarded the bid
- Protects against material defects
Rationale: A bid bond assures the project owner that the contractor
will honor the bid if selected.
- What is the main purpose of OSHA regulations for construction sites?
- Increase project speed
- Reduce material costs
- Ensure worker safety and health
- Regulate contractor profits
Rationale: OSHA standards are designed to prevent injuries, illnesses,
and fatalities on construction sites.
- Which of the following is required for a change order in a
- Verbal approval
- Contractor memo
- Written documentation signed by owner and contractor
- Email notification only
commercial project?
Rationale: Change orders must be documented in writing and agreed
upon by both parties to avoid disputes.