Residential Construction Superintendent Level 2 Certification Practice Exam Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf
- Which document primarily defines the scope of work for each
- Project schedule
- Purchase order
- Subcontract agreement
- Daily log
subcontractor?
Rationale: The subcontract agreement lists the exact tasks, materials, and
responsibilities assigned to each subcontractor.
- When excavating near an existing foundation, what is the most important
- Noise control 1 / 4
safety consideration?
- Equipment emissions
- Worker rotation
- Soil stability
Rationale: Soil stability prevents trench or wall collapse, which is the
leading hazard near foundations.
- What is the first step before pouring a concrete foundation?
- Install form boards
- Compact soil
- Place rebar
- Verify footing inspection approval
Rationale: Concrete cannot be poured until the inspector verifies footing
compliance with code and plans.
- Which schedule format best tracks progress across multiple trades?
- Bar chart
- Critical path method (CPM)
- Punch list
- Cost report
Rationale: CPM identifies task dependencies and the minimum project
duration, suitable for complex builds.
- A superintendent notices the plumbing rough-in deviates from plans.
- Notify the client
- Stop work and contact the project manager 2 / 4
What is the proper first action?
- Record in daily log only
- Continue until inspection
Rationale: The superintendent must halt incorrect work to avoid rework
and coordinate correction through management.
- Which OSHA standard regulates fall protection in residential
construction?
A. 1926.300
B. 1926.501
C. 1910.120
D. 1926.403
Rationale: OSHA 1926.501 outlines requirements for fall protection during
residential framing and roofing.
7. The purpose of a punch list is to:
- Schedule inspections
- Identify incomplete or defective work before final acceptance
- Document weather delays
- Estimate costs
Rationale: Punch lists itemize final corrections required before project
closeout.
- What determines the allowable spacing for framing members?
- Paint schedule
- Concrete strength
- Load and span 3 / 4
- Fastener type
Rationale: Spacing depends on design load and the span between supports
per building code.
- When preparing for a city inspection, who ensures compliance of all
- Architect
- Owner
- Superintendent
- Code official
installed systems?
Rationale: The superintendent coordinates subcontractors and verifies
readiness before the inspector arrives.
- Which type of insulation is most effective for irregular cavities?
- Rigid foam
- Batt
- Spray foam
- Reflective foil
Rationale: Spray foam expands to fill voids, providing superior air sealing
and coverage.
11. A “change order” is issued to:
- Record inspection
- Modify contract scope, cost, or schedule
- Approve material delivery
- Update safety plan
- / 4