North Dakota Class A General Contractor Licensing Exam Practice Test 100 Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf
- What is the primary purpose of the North Dakota State Building Code?
- To standardize construction materials
- To ensure minimum standards for health, safety, and welfare
- To regulate contractor wages
- To increase construction costs
Rationale: Building codes are designed to protect public health,
safety, and welfare by establishing minimum construction standards.
- Which entity issues the Class A General Contractor license in North
- Local building department
- North Dakota Secretary of State – Contractor Licensing
Dakota?
C. OSHA 1 / 4
- North Dakota Workforce Safety & Insurance
Rationale: The ND Secretary of State oversees contractor licensing
statewide.
- A Class A license in North Dakota allows a contractor to work on
projects valued:
- Up to $100,000
- Up to $500,000
- Up to $1 million
- Unlimited contract value
Rationale: Class A license holders are allowed to contract for projects
of any dollar amount.
- What is the minimum liability insurance coverage required for a Class
A license?
A. $50,000
B. $100,000
C. $200,000
D. $500,000
Rationale: Contractors must provide proof of at least $500,000
liability coverage as required by ND law.
- What must be included on all construction contracts?
- Contractor’s W-2
- Contractor’s spouse’s name
- Contractor’s license number 2 / 4
- Customer’s tax forms
Rationale: License numbers must appear on contracts and
advertising to ensure legitimacy and consumer protection.
- North Dakota lien laws allow a contractor to file a lien within how
- 30 days
- 60 days
- 90 days
- 180 days
many days after last furnishing labor or materials?
Rationale: ND statute sets a 90-day limit for filing a lien to secure
payment.
- The document that details who is responsible for each portion of work
on a project is:
- Punch list
- Fire certificate
- Scope of work
- Change directive
Rationale: Scope of work outlines contractor responsibilities and
deliverables.
- What best defines “substantial completion”?
- Project is fully painted
- Work is usable for intended purpose despite minor work
remaining 3 / 4
- All workers are paid
- Warranty period has ended
Rationale: Substantial completion means the owner can occupy or
use the facility.
9. OSHA requires fall protection at elevations of:
- 2 feet
- 4 feet
- 6 feet in construction
- 10 feet
Rationale: OSHA mandates fall protection beginning at 6 feet in
construction environments.
10. In cost-plus contracts, the contractor is paid:
- A fixed price only
- Actual cost plus a fee
- Only profit
- Only labor
Rationale: Cost-plus reimburses expenses plus contractor fee or
percentage.
11. The critical path in scheduling represents:
- Cheapest tasks
- Most manpower needed
- Longest duration path determining project completion time
- / 4