FDNY S56 Construction Site Fire Safety Manager (Citywide) Practice Exam Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf
- What is the primary responsibility of the Construction Site Fire Safety
- Supervise building inspectors
- File insurance paperwork
- Maintain site accounting records
- Ensure compliance with FDNY fire safety requirements
Manager (CSFSM)?
Ensuring compliance with FDNY-mandated fire safety measures is the core function of the CSFSM.
2. A hot work permit at a construction site is valid for:
- 8 hours
- 12 hours 1 / 4
- 24 hours
- One week
- Who may issue a hot work permit on a construction site?
- Any worker
- FDNY-certified Fire Guard (F-60) or CSFSM
- Site manager
- Building owner
FDNY requires hot work permits to be valid only for the calendar day of issuance (24 hours).
Only FDNY-certified personnel may issue the permit to maintain consistent fire prevention controls.
4. A fire watch during hot work must continue for at least:
- 15 minutes
- 30 minutes
- 60 minutes
- 3 hours
FDNY requires at least 1 hour of post-work monitoring due to smoldering fire risks.
5. Combustible waste must be removed:
- Once per week
- At the end of each shift
- Only when inspections occur 2 / 4
- Only after complaints
Regular removal prevents accumulation of fuel that increases fire load.
6. A standpipe system must remain:
- Partially operational
- Capped and unused
- In service at all times unless authorized otherwise
- Tagged out whenever construction occurs
- Who must be notified when a standpipe is impaired?
- The project accountant
- Only the subcontractor
- FDNY and site management
- The building owner only
- When must a fire safety logbook be updated?
- Weekly
- Monthly
- Only during inspections
- Daily or whenever fire safety events occur
FDNY mandates standpipes be operational for firefighting unless a variance is issued.
FDNY must be notified to ensure that emergency response is aware of reduced firefighting capability.
A current log ensures accurate tracking of site fire safety conditions. 3 / 4
9. Smoking on a construction site is:
- Allowed with permit
- Allowed in designated indoor areas
- Prohibited except in FDNY-approved outdoor areas
- Allowed anywhere outdoors
FDNY restricts smoking to reduce ignition risks.
10. Temporary heating equipment must be:
- Operated by any worker
- Stored anywhere
- FDNY-approved and properly supervised
- Allowed to run unattended
Only approved and supervised devices reduce heating-related fire hazards.
11. LPG cylinders must be stored:
- Inside the building
- Near exits
- In outdoor, secure, ventilated enclosures
- On rooftops
- What must be done before hot work begins?
- Notify the architect
- Complete a pre-work fire safety inspection
- Shut down all electrical power
- / 4
Outdoor storage prevents gas accumulation and allows safe ventilation.