NCCCO CORE EXAM PREP / – 100%
VERIFIED QUESTIONS AND CORRECT
ANSWERS | GRADE A EXAM REVIEW
- What is the minimum clearance distance for a crane operating near a 50 kV power
- 6 feet
- 10 feet
- 15 feet
- 20 feet
line, according to OSHA regulations?
Correct Answer: B
Rationale: OSHA 1926.1408 requires a minimum clearance of 10 feet for power lines up to 50 kV. For each additional 10 kV, the clearance increases by 0.4 inches. This ensures operator safety from electrical hazards.
- What is the primary purpose of a load chart in crane operations?
- To determine the crane’s fuel efficiency
- To calculate the crane’s maximum lifting capacity
- To schedule maintenance intervals
- To record operator certifications
Correct Answer: B
Rationale: The load chart provides the crane’s maximum lifting capacity based on boom length, angle, and radius, ensuring safe lifting within the crane’s limits.
- When inspecting a wire rope, what defect requires immediate replacement?
- Light surface rust
- Two broken wires in one strand
- Severe kinking or crushing
- Minor wear on outer wires
Correct Answer: C
Rationale: ASME B30.5 standards mandate immediate replacement of wire ropes with severe kinking, crushing, or birdcaging, as these defects compromise structural integrity and safety.
- What does the term "duty cycle work" refer to in crane operations?
- Continuous lifting operations without pauses
- Lifting loads at maximum capacity
- Periodic maintenance checks
- Operator training sessions
Correct Answer: A
Rationale: Duty cycle work involves repetitive, continuous lifting operations, such as pile driving or clamshell work, requiring specific load chart reductions to account for dynamic stresses. 1 / 2
- What is the standard hand signal for stopping all crane operations?
- Arm extended, palm down, moving side to side
- Both arms raised vertically
- Arm extended, fist clenched
- Hand tapping head
Correct Answer: A
Rationale: According to ASME B30.5, the standard stop signal is an extended arm with the palm down, moved side to side, ensuring clear communication to halt operations.
- What is the maximum allowable slope for crane setup to ensure stability?
- 1%
- 2%
- 5%
D. 10%
Correct Answer: A
Rationale: NCCCO and ASME B30.5 require the crane to be level within 1% to ensure load chart ratings are valid and to maintain stability during lifting.
- Who is responsible for determining the voltage of nearby power lines before crane
- The crane operator
- The site supervisor
- The utility company
- The rigger
operations begin?
Correct Answer: C
Rationale: OSHA 1926.1407 mandates that the utility company or a qualified person determines the voltage of power lines to ensure proper clearance distances are maintained.
- What is the primary function of outriggers on a mobile crane?
- To increase lifting capacity
- To stabilize the crane
- To extend the boom length
- To adjust the counterweight
Correct Answer: B
Rationale: Outriggers provide additional stability by increasing the crane’s base of support, reducing the risk of tipping during lifting operations.
- What should be done if a crane operator makes contact with a power line?
- Continue operations cautiously
- Stay in the crane until power is de-energized
- Immediately exit the crane
- Move the load away from the line
Correct Answer: B
Rationale: OSHA 1926.1408 advises operators to remain in the crane if it contacts a power line to avoid electrocution, until the utility company confirms the power is off.
- What is the effect of increasing the jib angle on a crane’s radius?
- Increases the radius
- Decreases the radius
- No effect on the radius
- / 2