NCCCO CORE Questions and Answers | Latest Update What is prohibited by OSHA 1926 Subpart cc regarding wire rope on a crane?✓ Splicing
What should be of major concern when considering surfaces for crane set up locations?✓ Voids, tanks, loose fill, depressions
Which items are included in the suspended weight when calculating parts of line?✓ Load weight, rigging, load block
What site condition must an operator be concerned about prior to setting up a crane?✓ Soil stability must be sufficient
What is an example of duty cycle crane operations?✓ High speed concrete placement
Where must barriers be erected in accessible areas to provide protection in the cranes work area? 1 / 2
- 0 2 4 / | © copyright | This work may not be copied for profit gain Excel!
- | P a g e | G r a d e A + | 2 0 24 / 2 0 2 5
✓ Within the equipment's rotating superstructure
According to ASME B30.5, How frequently is a crane operator required to have a physical?✓ Every 3 years
What is the result of rapid hoist acceleration?✓ Produces hook loads higher than actual weight
Wire rope lubricant should not:
✓ hinder visual inspection
On what principle is crane stability based?✓ leverage
Who must confirm that an overhead power line is de-energized?✓ Line owner