vA frequent inspection is:
Daily to monthly
- What action does a signal person intend the operator to perform if he extends his arm at shoulder
height, makes a fist with his hand, and sticks his/her thumb up?Boom Up (Appendix A to Subpart CC of Part 1926--Standard Hand Signals) Brainpower Read More Previous Play Next Rewind 10 seconds Move forward 10 seconds Unmute
0:02
/
0:15
Full screen
- When hoisting personnel, within what percentage of level must a telescopic boom crane be in order
- The load line of the crane you're operating contacts an energized power line. There's no sign of any
for the gross ratings in the load chart to remain valid?1% (1926.1431(c)(1) The equipment must be uniformly level, within one percent of level grade, and located on footing that a qualified person has determined to be sufficiently firm and stable.)
other danger, such as fire. What should you do? 1 / 2
Stay in the cab until the lines are de-energized.
- According to OSHA 1926.1413, how many randomly distributed broken wires in rotation-resistant
- broken wires in 6 rope diameters
- What is the net capacity of a crane on main boom unless the manufacturer states otherwise?
- / 2
rope are cause for replacement of the rope?
The capacity listed in the load chart minus the weight of the rigging and all attachments What may happen to a properly rigged load when lifted off the ground unless the operator takes account of boom deflection It could swing out away from the crane Who should an operator respond to a "stop" signal from?Anyone Which area do truck cranes without a 5th outrigger generally have no lifting capacity unless the manufacturer states otherwise?The front What is the definition of "operating radius?" The distance from the center of rotation of the crane to the center of gravity of the load What applies to the capacities below the bold line shown on a load chart?They are based on the stability of the crane In which quadrant are rough terrain crane capacities generally greater?Over the front According to federal requirements, under what conditions is it okay for a person to ride the headache ball?It is never okay By what percentage do most manufacturers require a crane's load chart capacity to be reduced by for duty cycle operations such as high-volume concrete placement?20% From which two points should the boom be measured?From the boom hinge pins to the center of the boom tip sheave What is the preferred method of installing wire rope from a reel onto a hoist drum?The rope runs from the top of the reel to the top of the drum