NCCCO MOBILE CRANE ( )

QUESTIONS WITH CORRECT

ANSWERS

  • When may blocking (cribbing) be placed under outrigger
  • beams?

  • When beams cannot be extended all the way out
  • To increase capacity
  • To improve stability
  • Never
  • d.

  • What is the result of placing timber blocking under the
  • tips of the tracks on a crawler crane?

  • Decreases the permitted capacity of the crane
  • Makes the crane more stable
  • Reduces the capacity of the crane
  • Makes the crane less stable
  • b.

  • / 4
  • According to ASME, what percentage of the
  • manufacturer's crane rating must not be exceeded if a load test is done on a repaired crane?

  • 110%
  • 85%
  • 75%
  • b.

  • Where is the tipping axis of a crawler crane located?
  • It is always at the centerline of the idler or sprocket
  • It depends if the idler or sprocket are in line or offset from
  • the track rollers

  • It is through the centerline of the crane cab
  • It is through the boom butt section
  • b.A long boom crane at a short radius and out of level by 300

can see a reduction incapacity by as much as:

50%

Crane stability is based on lever principle 2 / 4

What is the OSHA standard for cranes in construction industry?29 CFR-1926. Subpart CC

What are the requirements to be a crane inspector?Same as operator

What percentage of the crane chart is considered a critical lift?75%

A multi crane lift shall require Critical lift plan, reduction of gross capacity by 25% and one designated person in charge.

When doing a pick and carry, tire pressure must meet manufacturer's specifications

  • / 4

The load chart is matched to the crane by:

Serial number

Where do you find recommended reeving for the hoist lines?Owner's manual

Not extending telescoping boom sections equally; what may occur?Longer section collapse

What are the broken wire removal requirements for rotation resistant wire rope?

  • broken wires in 6 diameters or 4 in 30 diameters

How should wire rope be inspected during a frequent inspection?Visually

  • / 4

User Reviews

★★★★★ (5.0/5 based on 1 reviews)
Login to Review
S
Student
May 21, 2025
★★★★★

The step-by-step guides offered by this document enhanced my understanding. A impressive purchase!

Download Document

Buy This Document

$35.00 One-time purchase
Buy Now
  • Full access to this document
  • Download anytime
  • No expiration

Document Information

Category: EXAMS AND CERTIFICATIONS
Added: Dec 14, 2025
Description:

NCCCO MOBILE CRANE (ACTUAL ) QUESTIONS WITH CORRECT VERIFIED ANSWERS 26. When may blocking (cribbing) be placed under outrigger beams? a. When beams cannot be extended all the way out b. To increas...

Unlock Now
$ 35.00