NCCCO MOBILE CRANE Exam Queastions and Answers /
- What may happen to a properly rigged load when lifted off the ground unless the operator takes
- It could swing out away from the crane
- It could swing in towards the crane
- It could raise absolutely vertically
- It could shift in its rigging - CORRECT ANSWER-a.
account of boom deflection?
- What Standard Method hand signal is being illustrated?
- / 3
- Swing
- Stop
- Emergency Stop
- Travel - CORRECT ANSWER-a.
- Who should an operator respond to a "stop" signal from?
- Appointed signal person only
- Project manager only
- Superintendent only
- Anyone - CORRECT ANSWER-d.
- Which area do truck cranes without a 5th outrigger generally have no lifting capacity unless the
- The side
- The rear
- The front
- The outriggers - CORRECT ANSWER-c.
manufacturer states otherwise?
- What is the definition of "operating radius?"
- The distance from the base of the boom to the center of the load b. The distance from the front of the
- The distance from the center of rotation of the crane to the center of the load
- The distance from the center of rotation of the crane to the center of gravity of the load - CORRECT
crane to the center of gravity of the load
ANSWER-d.
- What applies to the capacities below the bold line shown on a load chart?
- They are based on the structural strength of the crane
- They must not be used
- They are based on the stability of the crane 2 / 3
- They should only be used if the crane is set up on outriggers - CORRECT ANSWER-c.
- In which quadrant are rough terrain crane capacities generally greater?
- Over the front
- Over the rear
- Over the right side
- Over the left side - CORRECT ANSWER-a.
- According to federal requirements, under what conditions is it okay for a person to ride the headache
- When there is no other way to gain access
- When the lift has been approved by an engineer
- When other means would be more dangerous
- It is never okay - CORRECT ANSWER-d.
ball?
- By what percentage do most manufacturers require a crane's load chart capacity to be reduced by for
- 10%.
- 15%.
- 20%.
- 30%. - CORRECT ANSWER-c.
duty cycle operations such as high-volume concrete placement?
10.which two points should the boom be measured?
- From the base of the boom to the center of the boom tip sheave
- From the boom hinge pins to the boom tip
- From the boom hinge pins to the center of the boom tip sheaved. d. From the base of the boom to the
- What action does a signal person intend the operator to perform if he extends his arm at shoulder
- Boom down
- / 3
boom tip - CORRECT ANSWER-c.
height, makes a fist with his hand, and sticks his/her thumb up?