NCCCO Mobile Crane Exam ( / ) Questions and 100% Correct Verified Answers| Grade A
.1. What action does a signal person intend the operator to perform if he extends his arm at shoulder height, makes a fist with his hand, and sticks his/her thumb up?
- Boom down
- Swing
- Boom up
- Extend boom - ANSWER-c.
.1. Where must the operator's manual be kept during crane operations?
- The operator's manual must be kept in a location that is readily available
- The operator's manual must be kept in the cab at all times
- The operator's manual must be kept in the dispatch office
- The operator's manual must be kept in a secure place - ANSWER-b.
.10. What is the definition of "operating radius?"
- The distance from the base of the boom to the center of the load b. The distance from the front of the
- The distance from the center of rotation of the crane to the center of the load
- The distance from the center of rotation of the crane to the center of gravity of the load - ANSWER-d.
crane to the center of gravity of the load
.10. What shall be in the operators cab during crane operations?
- load charts
- Inspection reports
- Hand signal chart
- The crane log - ANSWER-a. 1 / 3
.11. What applies to the capacities below the bold line shown on a load chart?
- They are based on the structural strength of the crane
- They must not be used
- They are based on the stability of the crane
- They should only be used if the crane is set up on outriggers - ANSWER-c.
.11. Which of the following is considered duty cycle work?
- Pile- driving
- Setting trusses
- Clam - Shell digging
d Unloading trucks - ANSWER-c.
.12. In which quadrant are rough terrain crane capacities generally greater?
- Over the front
- Over the rear
- Over the right side
- Over the left side - ANSWER-a.
.12. When doing cycle work, the load chart must be reduced by how much?
- 50%
- 20%
- 30%
- none - ANSWER-b.
.13. According to federal requirements, under what conditions is it okay for a person to ride the headache ball?
- When there is no other way to gain access
- When the lift has been approved by an engineer 2 / 3
- When other means would be more dangerous
- It is never okay - ANSWER-d.
.13. Which components are not parts of the boom?
- Lacing
- Cords
- Cross members
- Heel pins - ANSWER-d.
.14. By what percentage do most manufacturers require a crane's load chart capacity to be reduced by for duty cycle operations such as high-volume concrete placement?
- 10%.
- 15%.
- 20%.
- 30%. - ANSWER-c.
.15. From which two points should the boom be measured?
- From the base of the boom to the center of the boom tip sheave
- From the boom hinge pins to the boom tip
- From the boom hinge pins to the center of the boom tip sheaved. d. From the base of the boom to the
boom tip - ANSWER-c.
.16. What is the preferred method of installing wire rope from a reel onto a hoist drum?
- The rope runs from the top of the reel to the bottom of the drum
- The rope runs from the bottom of the reel to the top of the drum
- The rope runs from the top of the reel to the top of the drum
- There is no preferred method - ANSWER-c.
.17. Over which quadrant are truck crane capacities usually greater?
- / 3