- What action does a signal person intend the operator to perform if
- Boom down
- Swing
- Boom up
- Extend boom - ANSWER-c.
he extends his arm at shoulder height, makes a fist with his hand, and sticks his/her thumb up?
- When hoisting personnel, within what percentage of level must a
- 1%
- 2%
- 5%
- 8% - ANSWER-a.
telescopic boom crane be in order for the gross ratings in the load chart to remain valid?
- The load line of the crane you're operating contacts an energized
- Climb down carefully from the crane cab 1 / 3
power line. There's no sign of any other danger, such as fire. What should you do?
- Jump down, feet together
- Stay in the cab until the lines are de-energized
- Get as far away from the crane as possible - ANSWER-c.
- According to OSHA 1926.1413, how many randomly distributed
- 1 broken wire in 6 rope diameters
- 2 broken wires in 30 rope diameters
- 3 broken wires in one strand in one lay
- 2 broken wires in 6 rope diameters - ANSWER-d.
broken wires in rotation-resistant rope are cause for replacement of the rope?
- What is the net capacity of a crane on main boom unless the
- The capacity listed in the load chart minus the weight of the
- The capacity listed in the load chart plus the weight of the rigging
- The capacity listed in the load chart minus the weight of the rigging
- The capacity listed in the load chart minus the weight of the
manufacturer states otherwise?
rigging and all attachments
and all attachments
and all attachments not in use
rigging alone - ANSWER-a.
- What may happen to a properly rigged load when lifted off the
- It could swing out away from the crane 2 / 3
ground unless the operator takes account of boom deflection?
- It could swing in towards the crane
- It could raise absolutely vertically
- It could shift in its rigging - ANSWER-a.
- What Standard Method hand signal is being illustrated?
- Swing
- Stop
- Emergency Stop
- Travel - ANSWER-a.
- Who should an operator respond to a "stop" signal from?
- Appointed signal person only
- Project manager only
- Superintendent only
- Anyone - ANSWER-d.
- Which area do truck cranes without a 5th outrigger generally have
- The side
- The rear
- The front
- The outriggers - ANSWER-c.