- What action does a signal person intend the operator to perform if he extends his
- Boom down
- Swing
- Boom up
- Extend boom - CORRECT ANSWER - c.
arm at shoulder height, makes a fist with his hand, and sticks his/her thumb up?
- When hoisting personnel, within what percentage of level must a telescopic
- 1%
- 2%
- 5%
- 8% - CORRECT ANSWER - a.
boom crane be in order for the gross ratings in the load chart to remain valid?
- The load line of the crane you're operating contacts an energized power line.
- Climb down carefully from the crane cab
- Jump down, feet together
- Stay in the cab until the lines are de-energized
- Get as far away from the crane as possible - CORRECT ANSWER - c. 1 / 4
There's no sign of any other danger, such as fire. What should you do?
- According to OSHA 1926.1413, how many randomly distributed broken wires in
- 1 broken wire in 6 rope diameters
- 2 broken wires in 30 rope diameters
- 3 broken wires in one strand in one lay
- 2 broken wires in 6 rope diameters - CORRECT ANSWER - d.
rotation-resistant rope are cause for replacement of the rope?
- What is the net capacity of a crane on main boom unless the manufacturer states
- The capacity listed in the load chart minus the weight of the rigging and all
- The capacity listed in the load chart plus the weight of the rigging and all
- The capacity listed in the load chart minus the weight of the rigging and all
- The capacity listed in the load chart minus the weight of the rigging alone -
otherwise?
attachments
attachments
attachments not in use
CORRECT ANSWER - a.
- What may happen to a properly rigged load when lifted off the ground unless the
- It could swing out away from the crane
- It could swing in towards the crane
- It could raise absolutely vertically
- It could shift in its rigging - CORRECT ANSWER - a.
- / 4
operator takes account of boom deflection?
- What Standard Method hand signal is being illustrated?
- Swing
- Stop
- Emergency Stop
- Travel - CORRECT ANSWER - a.
- Who should an operator respond to a "stop" signal from?
- Appointed signal person only
- Project manager only
- Superintendent only
- Anyone - CORRECT ANSWER - d.
- Which area do truck cranes without a 5th outrigger generally have no lifting
- The side
- The rear
- The front
- The outriggers - CORRECT ANSWER - c.
capacity unless the manufacturer states otherwise?
- What is the definition of "operating radius?"
- The distance from the base of the boom to the center of the load b. The distance
- The distance from the center of rotation of the crane to the center of the load 3 / 4
from the front of the crane to the center of gravity of the load
- The distance from the center of rotation of the crane to the center of gravity of
the load - CORRECT ANSWER - d.
- What applies to the capacities below the bold line shown on a load chart?
- They are based on the structural strength of the crane
- They must not be used
- They are based on the stability of the crane
- They should only be used if the crane is set up on outriggers - CORRECT
ANSWER - c.
- In which quadrant are rough terrain crane capacities generally greater?
- Over the front
- Over the rear
- Over the right side
- Over the left side - CORRECT ANSWER - a.
- According to federal requirements, under what conditions is it okay for a
- When there is no other way to gain access
- When the lift has been approved by an engineer
- When other means would be more dangerous
- It is never okay - CORRECT ANSWER - d.
person to ride the headache ball?
- By what percentage do most manufacturers require a crane's load chart capacity
- / 4
to be reduced by for duty cycle operations such as high-volume concrete placement?