When using a remote or radio control, it is important to? change battery at beginning of shift
Before using rigging, the operator should be aware of the? highest capacity rating
Overhead cranes should be parked in? an area where it will not cause an unsafe condition
What should you do when the hook or load is moving above personnel? sound a warning signal
Cranes shall not be used for side pulls unless? specifically authorized by a responsible person
- / 3
According to OSHA, power supply to the runway shall be controlled by? the switch or circuit breaker
ASME B30 standards are designed to? recommend safety
What is the ASME volume that pertains to overhead cranes?
B30.2
The hoist limit switch which controls the upper limit of the load block.. (finish phrase) shall not be used as an operating control
According to OSHA, what type of chain should be used by an overhead crane? alloy
According to ASME B30.2, the removal criteria for regular lay wire rope is four broken wires in one strand, in one lay or twelve randomly distributed broken..(finish phrase) 2 / 3
wires in one lay
Which OSHA regulation listed below can you find information about hoisting slings?
- 1910.184
- 1910.550
- 1910.180
- 1910.601
1910.184
When given the signal (stop signal), what will the operator do? bridge travel
If the load does not balance after raising it off the floor, what steps should you take? lower to the floor and adjust the rigging
According to OSHA, frequent inspections are to be performed at what intervals? daily to monthly
If a crane is modified and re-rated it must be checked thoroughly by a?