Question 1:
What should be checked for proper fluid level in hydraulic systems?
Correct Answer: D - Hydraulic systems
Explanation: Hydraulic systems require proper fluid levels to ensure
efficient operation and to avoid potential damage caused by insufficient lubrication or cooling.
Question 2:
Who is responsible for determining if the load weight does not exceed the crane rating at the designated radius for lifting?Correct Answer: B - Person responsible for lift 1 / 3
Explanation: It is the responsibility of the person in charge of the lift to
ensure the load weight is within the crane's rated capacity for the given radius, ensuring safe lifting operations.
Question 3:
Where should climbing instructions be kept on a site?
Correct Answer: D - In the crane cab
Explanation: Climbing instructions must be readily accessible and are
typically kept in the crane cab for immediate reference during operations.
Question 4:
What is the main power switch location for a tower crane?
Correct Answer: D - Base of crane
Explanation: The main power switch is generally located at the base of
the tower crane to facilitate easy access for power control or in emergencies.
Question 5:
What is the minimum clearance required between power lines rated at 175KV and any part of the crane or load?
Correct Answer: C - 15 feet
Explanation: A minimum clearance of 15 feet is required to prevent
electrical hazards when operating near power lines with a rating of
175KV. 2 / 3
Question 6:
What is the minimum number of voice signal elements in each series when lifting personnel?
Correct Answer: D - 2
Explanation: Clear communication is critical, and a minimum of two
voice signal elements per series ensures clarity and safety during personnel lifting.
Question 7:
What is the condition when the tower load block or hook assembly comes in contact with the upper part of the tower?
Correct Answer: B - Overtravel
Explanation: Overtravel occurs when the load block or hook assembly
makes contact with the upper part of the tower, potentially leading to unsafe conditions.
Question 8:
What is the minimum pitch diameter for load hoisting sheaves according to ASME B30.3?
Correct Answer: C - Less than 18 times rope diameter
Explanation: ASME B30.3 specifies that the pitch diameter of load
hoisting sheaves must be at least 18 times the diameter of the rope to ensure proper functionality and safety.