ACI Concrete Flatwork Finisher/Technician Practice Exam Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf
- Which of the following is the primary purpose of finishing concrete?
- To increase its compressive strength
- To produce a smooth, level, and uniform surface
- To reduce water-cement ratio
- To speed up curing
Rationale: Finishing is performed to achieve a flat, smooth, and
uniform surface suitable for its intended use.
- What is the ideal slump range for a typical flatwork slab using a normal
- 0–1 inch
- 1–2 inches
- 3–4 inches 1 / 4
concrete mix?
- 5–6 inches
Rationale: A slump of 3–4 inches provides good workability for
placement and finishing without excessive bleeding.
- Which tool is typically used for screeding freshly placed concrete?
- Trowel
- Straightedge
- Bull float
- Edger
Rationale: A straightedge is used to strike off excess concrete and
create a level surface.
- What is the purpose of using a bull float?
- Compact concrete
- Smooth the surface and embed aggregate
- Measure slab thickness
- Apply curing compound
Rationale: Bull floating helps to smooth the concrete surface and
bring fine material to the top.
- Which finishing technique helps reduce the likelihood of surface
- Using high water content
- Delaying finishing operations
- Proper timing of finishing and control joints
- Excessive troweling 2 / 4
cracking?
Rationale: Timely finishing and placement of control joints relieve
shrinkage stress and reduce cracking.
- What is the typical spacing of contraction joints in a concrete slab?
- 2–4 feet
- 5–7 feet
- 8–12 feet
- 15–20 feet
Rationale: Contraction joints are typically spaced 8–12 feet apart to
control cracking due to shrinkage.
- Which of the following is used to create a smooth, hard, and dense
- Screed
- Edger
- Steel trowel
- Shovel
surface after floating?
Rationale: Steel troweling densifies the surface, producing a smooth
and hard finish.
- When is hand troweling typically performed on a slab?
- Immediately after placement
- After initial set and floating
- Before screeding
- After curing 3 / 4
Rationale: Hand troweling is done after the concrete has stiffened
enough to support the trowel without leaving marks.
- What is the primary function of a concrete edger?
- Screed the concrete
- Compact the concrete
- Round the edges of a slab
- Apply curing compound
Rationale: Edgers create a rounded edge to prevent chipping and
improve durability.
- What is a common cause of surface scaling on concrete?
- Low cement content
- High air content
- Freezing and thawing of saturated surface
- Excessive troweling
Rationale: Scaling occurs when water in the surface layer freezes,
causing surface flaking.
- Which type of concrete finish is typically applied to driveways
- Smooth trowel finish
- Exposed aggregate finish
- Broom finish
- Steel trowel finish
- / 4
for slip resistance?