SCRUM PSM 2 Exam (Latest Update 2025 / 2026) Questions & Answers | Grade A | 100% Correct (Verified Solutions)
Question:
T/F: During the Sprint Review, the Product Backlog may also be adjusted
Answer:
True
During the Sprint Review event, the Scrum Team and stakeholders review what was accomplished in the Sprint and what has changed in their environment. Based on this information, attendees collaborate on what to do next. The Product Backlog may also be adjusted to meet new opportunities.The Sprint Review is a working session, and the Scrum Team should avoid limiting it to a presentation.
- / 4
Question:
T/F: The Product Owner cannot work as a Developer in a Scrum Team
Answer:
False
If the Product Owner or Scrum Master are actively working on items in the Sprint Backlog, they participate as Developers.
Question:
T/F: Each increment is independent of the previous increment
Answer:
False
An Increment is a concrete stepping stone toward the Product Goal. Each Increment is additive to all prior Increments and thoroughly verified, ensuring that all Increments work together. In order to provide value, the Increment must be usable.
- / 4
Question:
Which of the following Scrum events should be held at the same time and place?
- All Scrum events
B.Backlog Refinement C.Sprint Retrospective D.Sprint Review E.Sprint Planning F.Sprint Planning, Daily Scrum and Sprint Retrospective. The Sprint Review will change depending on the availability of the Stakeholders.
Answer:
A.All Scrum events
Optimally, all events are held at the same time and place to reduce complexity.
Question:
What is identified by the end of the Sprint Retrospective?
A.Improvements for the company B.The most helpful changes to improve its effectiveness C.The most important features 3 / 4
D.The most important problems
Answer:
B.The most helpful changes to improve its effectiveness
The purpose of the Sprint Retrospective is to plan ways to increase quality and effectiveness. The Scrum Team identifies the most helpful changes to improve its effectiveness.
Question:
When is the Sprint Goal created?
A.During the Sprint Review with the Stakeholders B.During the Sprint as more is learned C.During Release planning D.During Sprint Goal refinement E.During the Sprint Planning
Answer:
E.During the Sprint Planning
The Sprint Goal is created during the Sprint Planning event and then added to the Sprint Backlog.
- / 4